DLTJ-05 非开挖电缆管道作业指导书

非开挖电缆管道作业指导书

编码:DLTJ-05

中国南方电网有限责任公司电网建设施工作业指导书

1 适用范围······················································································································································497

2 编写依据······················································································································································497

3 作业流程图··················································································································································497

4 安全风险辨析与预控··································································································································497

5 作业内容······················································································································································498

DLTJ-05 非开挖电缆管道作业指导书

1 适用范围

本节适用于穿越无法开挖或不宜开挖的35kV及以下配网工程地下电缆管道施工。

2 编写依据 序号 1 2 3 引用资料名称 GB 50168—2006《电气装置安装工程电缆线路施 工及验收规范》 Q/CSG 11105—2008《南方电网工程施工工艺控制 规范》 《中国南方电网有限责任公司基建工程质量控制作 业标准(WHS)》 第七章 第五节 表2-1 编 写 依 据

相关章节条款 3 作业流程图

图 3-1 作业流程图

4 安全风险辨析与预控

表4-1 工作前安全风险辨析及预控措施表

序号 安全风险 预 控 措 施

基坑开挖时应保持安全距离,设专人监护,将基面上浮石、松石或坑边 浮石、土块清除掉,避免施工时活石掉下砸伤人

检查结果

1 物体打击

采用打风镐等机械方式开挖水泥路时,施工人员应戴安全帽、手套与面 罩。采用人工方式,打铁锤人应站在扶凿人的侧面,不得戴手套,并应采 取有效防围措施防止石块弹起伤人

中国南方电网有限责任公司电网建设施工作业指导书

表4-1(续)

序号 安全风险 预 控 措 施 避开中午炎热时间段户外作业 检查结果 2 中暑 配置太阳伞,室内配置排风扇,人员轮流休息 供应清凉含盐饮料 加强使用前及使用过程中的检查,保护零线与工作零线不得混接,开关 箱漏电保护器灵敏可靠,漏电保护装置参数应匹配,严格执行“一机、一 闸、一漏、一箱”的要求 3 触电 用电管理和检修维护必须规范,并由专业电工进行,配电箱必须上锁, 并采取防雨措施 发电机、顶管机等机械使用前应将外壳安装保护接地线 工作间断时切断电源 烧焊作业时要戴防护眼镜、脚罩、手套

4

灼烫 严格执行持证上岗制度,焊工必须持证上岗 请您认真检查并签名确认,您的签名意味着将承担相应的安全质量责任。 施工单位检查人: 日期:

监理单位检查人: 日期:

注:对存在风险且控制措施完善填写“√”,存在风险而控制措施未完善填写“×”,不存在风险则填写“―”,未检 查项空白。

5 作业内容 5.1 作业前施工条件

序号 1 2 3 4 5 项目 任务单 相关证照 工程合同 或协议 图纸 施工方案 表5-1 作业 前施 工条 件

内 容 根据本单位实际设置内容(包含本项工作) 根据需要办理涉及进入工作场所的手续、证件 合同及安全协议 设计图纸 施工措施、安全技术交底(项目部级) 确认人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 说明 经审批 有效 有效 经审批 经审批

DLTJ-05 非开挖电缆管道作业指导书

5.2 施工准备

序号 项目 表5-2 施 工 准 备

内 容 说 明 定向钻铺管施工操作人员必须经培训考核 合格后,方能上岗操作施工,同时应遵守相应 的安全操作技术规程。技术岗位必须持有与作 业工种相应、有效的上岗证 管材:高密度聚乙烯管;其他材料:护壁泥 浆、充填泥浆应符合设计要求。管材有出厂合 格证明。定向钻铺设钢管应具有足够强度、韧 性、良好的焊接性能和抗腐蚀能力,符合国家 有关现行标准及相应规定 根据现场情况使用的工器具、机械符合相关 要求。仪器、仪表使用前必须经有资质的单位 检验合格且在检测有效期内才能使用 非开挖电缆管道工作前安全风险辨析及预 控措施表将随本单位安全生产风险管理体系 的建设和推进不断完善扩展。作业风险包括安 全、职业健康和环境三方面 施工准备完成后可报开工,当施工准备不足 时,上报该项目负责人协调解决 1 人员配置 施工员、定向钻铺管施工操作人员等 2 施工内容 管材:定向钻铺管使用管材通常为HDPE 管; 相对应的设 其他材料:护壁泥浆、充填泥浆等 备材料 3 施工内容 相对应的器 施工所需的工器具、机械、测量仪器等定向钻 具、机械及工 铺管钻机等 器具仪表 现场施工负责人参照本单位安全生产风险管理 体系的作业风险基准库内与本工序相关的风险及 控制措施、施工方案、现场情况等因素生成并填 写非开挖电缆管道工作前安全风险辨析及预控措 施表(见表4-1) 4 作业风险 控制 5 完成开工 程序 工作负责人向项目负责人报开工,并由项目负 责人完成向监理单位开工报审手续 5.3 主要作业内容

表5-3 主 要 作 业 内 容

序号 项目 内 容 说 明

1

(1) 技术准备:

1)定向钻铺管施工前应进行工程勘察。工程勘察应符合GB 50021— 2001《岩土工程勘察规范》、DBJ 08-37—1994《岩土工程勘察规范》和 CJJ 61—2003《城市地下管线探测技术规程》的规定。 2)地下管线复查并在地面上做出标记。

3)根据地下管线复查结果调整钻孔设计轨迹。 4)选定出、入钻点,开挖出、入钻工作沟。

5)绘制出详细的地下管线勘察成果图,作为钻孔轨迹设计的依据。 6)入钻点和出钻点的选取:根据设计要求,入钻点宜设在行人车辆稀 少且有足够空间摆放设备处,出钻点则宜设置在能够摆放管材、方便拖 按安规规定佩戴统 管的另一端。 一的安全帽,统一佩戴 7)钻孔轨迹设计要求根据取得地下管线勘察成果、现场地形地貌和周 作业前工作 有个人照片的作业证 边环境信息。钻杆最小弯曲半径等技术资料。其中钻孔轨迹参数包括入 (或胸卡证),穿着统一 钻角i、出钻角o、入钻造斜段 Li、中间水平段L'、出钻造斜段 Lo、钻 的工作服 孔深度H 等。钻孔轨迹(见图5-3-1)。

图5-3-1 钻孔轨迹示意图

中国南方电网有限责任公司电网建设施工作业指导书 第 4 部分:配网工程

表5-3(续)

序号 项目 内 容 说 明

1

8)编制施工方案,准备好相关的施工记录表。

(2) 现场施工负责人向进入施工范围内所有人员详细交待本次施工 作业内容、进度要求、特殊项目施工要求、作业标准、安全注意事项、 危险点及控制措施、危害环境的相应预防控制措施、人员分工,并签署

作业前工作 (班组级)安全技术交底。

(3) 现场施工负责人负责办理相关的工作许可手续,开工前做好现场 施工防护围蔽警示措施;夜间施工的须有足够的照明。

(4) 现场施工负责人检查所有工作人员是否正确使用劳保用品及着 装,并带领施工作业人员进入作业现场 作业

钻沟、下管 开挖应严格按挖沟断面分级开挖,沟体开挖应连续进行,挖出土方应 沟开挖 及时外运,不得随意堆放

(1) 导向孔施工应按事先设计好的钻孔轨迹进行导向施工,并做好导 向孔施工的记录。

(2) 导向孔施工时,通过地面上的手持式导向仪,随时测量出孔底钻 头深度和角度等参数,掌握孔内情况,随时进行控制和调整。每钻完一 根钻杆要测量一次钻头的实际位置,以保证导向孔符合设计要求。导向 钻孔轨迹与既有地下管线的最小安全距离如下表所示。

平行净距 交叉净距

2 3

4

≤1000mm ≤1000mm

导向孔施工 给水管 1.5 2.0 1.5 2.0

排水管 1.0 1.5 1.0 1.5 热力管 2.0 2.5 1.5 2.0 煤气管 3.5 4.0 2.0 2.0 输油管 3.5 4.0 2.0 2.5 电力电缆 3.0 3.5 1.5 2.5 通信电(光)缆 3.0 3.5 1.5 2.0 (3)定向钻铺管工程应符合国家及地方有关城市规划、土地管理、环 境保护等法律法规的规定

(1) 热熔对接是将待连接的管材(件)两端面刨平,用加热板加热, 使塑管端面熔化,在一定的压力作用下,使熔化端面接触,熔融体互融, 从而完成管道连接。

(2) 一般情况下,对接熔的整个过程分为五个阶段:预热阶段(即卷 边阶段);吸热阶段;转换阶段(即加热板抽出阶段);熔接阶段;冷却 阶段。

个卷边,卷边的高度因管材的规格不同而不同,卷边的高度将决定最终 焊环的环形。

2)吸热阶段:在这个阶段中,热量在所要连接的管材内扩散,这个阶 段需要施加一个较小的压力。

3)加热板取出阶段:这个阶段用来在将所连接的管材或管件接触之前, 取出加热板。取出加热板和使连接管材相接触的时间越短越好,以避免 热量损失或熔融端面被污染(灰尘、沙)氧化等。 现场施工负责人发出许可开工命令

5

开始主要

DLTJ-05 非开挖电缆管道作业指导书

序号

项目

表5-3(续)

内 容

4)熔接阶段:即纯粹的熔接,将要连接的管材熔化端面相互接触,按 所选择的标准逐渐建立和保持对接压力。

5)冷却阶段:冷却过程按标准规范施以特定压力,注意不能有张力和 机械应力,否则会影响熔接质量。冷却阶段所施加的压力有时与焊接压 力相同,但主要依据使用标准而定。

6)高密度聚乙烯管(HDPE)的加热熔接温度为 220℃,各阶段所用 时间T和压力 P取决于所使用的管材标准,施工中,主要采用SHD—250 塑料管道热熔对接机

说 明

5 管材焊接

6

扩孔、清孔 施工

(1) 在导向孔施工完成后,进行扩孔施工。扩孔的直径一般为所要敷 设管道的外包络直径的1.2~1.5 倍。当扩孔的直径较大时,需要用不同 直径的扩孔钻头从小到大逐级将导向孔扩大至设计终孔直径(例如,设

现场施工负责人正

计扩孔终孔直径为用650mm 时,那么在扩孔施工时就要分别用直径

确、安全地组织作业,

250mm、350mm、450mm、550mm、650mm的扩孔钻头进行分

现场施工质安员负责 级扩孔)。扩孔时,不停地在扩孔钻头后方接上钻杆,使整个钻孔内始终

现场作业全过程的安

都有钻杆。当某一级扩孔钻头回扩到入钻沟后,将扩孔钻头拆卸后,在

全质量监控

出钻沟一端再接上下一级扩孔钻头,进行回扩,依此反复直到设计孔径。 (2) 在扩孔的同时要不断向孔内注入化学泥浆,以便排出扩孔时所切 削下来的泥土、钻屑,防止孔壁坍塌以及减小回拖阻力

7 回拉放管

(1) 将钻杆、扩孔钻头和被安装管线依次连接好,回拖入孔内。由于 孔内充满泥浆,所以管线是处于悬浮状态的,管与孔壁之间由于泥浆润 滑作用,减少了回拖阻力,当管道全部被拖入孔内后,拖管完成。

(2) 化学泥浆的制作:施工时,通过钻杆向孔底不停地泵入化学泥浆。 化学泥浆的配制见下表。

地层 黏土、亚黏土 粉砂、细砂 中、粗砂 (S/qt)

5.4 质量检验

表5-4 质 量 检 验

序号 项目 内 容

(1) 入钻口、出钻口不超过规划红线。 (2) 管径大小、数量要满足电缆敷设要求。 (3) 管道畅通。

(4) 出线点要与设计选取点吻合。

(5) 施工时和施工完成后,铺设管线的上覆土层及相邻建筑物不得沉陷、坍塌或隆起, 相邻或相交管线及地下构筑物不受损坏。

(6) 复测导向钻孔起迄点的平面位置和高程是否符合设计要求。

(7) 导向孔轨迹测量应采用导向仪随钻测控深度、顶角、方位角、工具面向角等基本参 数。

1 本工序工艺自检 (8) 实钻导向孔轨迹应符合设计轨迹要求,偏差应在设计允许范围内。

(9) 配制泥浆现场检测应包括下列内容: 1)采用pH 值试纸检测配浆用水的pH 值。

2)采用泥浆密度计或泥浆密度秤检测泥浆密度。 3)采用马氏漏斗检测泥浆黏度。

4)采用气压式失水仪检测泥浆失水量。

(10)PE管连接的质量应符合相关技术标准的规定。

(11)根据定向钻铺设的生产管类型,应按相应的检验方法进行质量验收。 马氏漏斗黏度1)铺设电力管(管内径 ≥98mm)的工程,宜选用定径(长)试通棒检测验收: 30~40 40~55 50~65 a)定径试通棒可选用木质或铁质材料制作。

501

中国南方电网有限责任公司电网建设施工作业指导书 第 4 部分:配网工程

表5-4(续)

序号 项目 内 容 b)定径试通棒的直径可由D=1.25d 确定(其中D为生产管的公称内径,d 为试通棒直径)。 c)定径试通棒长度为0.45m。 2)铺设电力管(管内径<98mm)的工程,宜选常用的玻璃钢质制成的通管器检测验收, 通管径直径为15mm (12)除以上要求外本工序完成后,现场工作负责人按GB 50168—2006《电气装置安装工 程电缆线路施工及验收规范》中4.1、5.3 中的规定和根据表5.4 中序号2 质量控制点要求生 成相关表格,并组织检验 1 本工序工艺自检

质量控制点 序号 控 制 点 所用机械、设备、材料的品种、级 别、规格和数量 管材焊接 扩孔、清孔 回放拉管 工序验收检查 控 制 方 式 W ● ● ● ● H S 1 2 3 4 5 完成本工序提交 给下一道工序 ● 2 3 收集、整理、移交本工序相关资料 注:质量控制点中H:停工待检点;W:见证点;S:旁站点。